December 4, 2020
Construction will begin December 14, 2020. The work plan is as follows:
Phase 1 Riverbank Works
Construction start: |
December 14, 2020 |
Construction end: |
April 2021 |
Work: |
Site preparation including tree removal works, stabilization of riverbank along Wellington Crescent from Doncaster Street to Assiniboine Park, outfall works at Park Boulevard and Doncaster Street, and underground utility relocations along Wellington Crescent. |
Wellington Crescent will be closed to all traffic during Phase 1. Sidewalks, emergency services access, and access to private approaches will be maintained, as will the east entrance of Assiniboine Park.
Portions of the existing walking and cycling pathway will be closed as construction progresses. A temporary multi-use pathway will be provided for walking and cycling through the area. Please observe and follow detour signage while walking or cycling through the site.
Phase 2 Road and Path Relocation Works
Construction start: |
May 2021 |
Construction end: |
October 2021 |
Work: |
A second construction notice with details regarding closures and detours will be provided in advance of the start of Phase 2. |